What are the risks of buying off-plan?
The main ones are late delivery, changes in design or finishes, the developer's financial problems and the market not rising as projected. You reduce them by buying from developers with a proven delivery record, with a trust or escrow account, complete permits and a contract with clear penalties for delays.
What happens to my money if the developer goes bankrupt or abandons the project?
It depends on how the project is structured. If there is a trust under Law 189-11, the land and the buyers' payments are in the name of a trustee, separate from the developer's assets, and the trust agreement defines what happens if construction stops. If you paid the company directly with no trust or escrow account, you are usually just one more creditor and would have to file a legal claim, with an uncertain outcome.
That is why, before signing, you should ask for the trust agreement and read exactly what the trustee controls.
Example: how much money you have at risk during construction
An illustration, not a real case. A USD 150,000 unit with a plan of 10% between reservation and signing, 40% in installments over 24 months and 50% on delivery. When construction is finished you will have paid USD 75,000 without yet having the unit. That is the amount you need to protect: the more closely each payment is tied to actual construction progress and to an account controlled by a third party, the lower your risk.
Which contract clauses should I review when buying off-plan?
- Delivery date, grace period and penalty for each month of delay.
- The right to terminate and recover what you paid if the delay exceeds a limit.
- Force majeure: it should be specific and not usable to justify any delay.
- Permitted changes to design, square footage and finishes, with a specifications annex.
- What happens if you are the one who misses a payment: penalties and the percentage you could lose.
- Conditions for assigning the contract to another buyer before delivery.
- Warranties for construction defects after delivery.
How do I verify that the project's permits are in order?
There is also market risk: if many identical units come up for sale or rent at the same time on delivery, prices can come under downward pressure. No contract eliminates that risk; you can only reduce it by choosing the location and the product well.
- The building permit from the Ministry of Housing, Habitat and Buildings.
- The environmental permit or authorization from the Ministry of Environment.
- A surveyed land title in the name of the developer or the trustee, and a Certification of Legal Status with no unexpected liens.
- The CONFOTUR resolution, if the project promises one.
- Projects already delivered by the same developer that you can visit.
Updated:
These answers are for guidance only and do not replace advice from a lawyer, accountant or immigration adviser. Laws, rates and amounts can change: confirm each case before signing or paying.
Properties you may like
See more properties →More on Buying pre-construction (off-plan)
Can't find your question?
Write to us and a RE/MAX Atlantis adviser will answer in your language.
Ask a question